TS3016
Installation, details, options

For a larger view, please mouseover the image.
Operating and installation diagram for a TS3016 system.

The TS vessel must always be installed higher than the mechanical seal. The buffer/barrier fluid flows via the rising pipe into the vessel and is cooled. Particularly with natural circulation, the fluid level must always be higher than the rising pipe to maintain the circulation and to provide the specified cooling capacity. Connection pipes to the seal should be designed with as little resistance as possible.

Cleaning:
To clean the inside of the vessel you simply have to open the union nut, disconnect the gas supply and level switch, and lift the vessel case. There is no need to dismantle the seal and cooler connections or the lase.

1 Pressure gauge
2 SPS Level switch
3 From PCV, we recommend using a reverse controlled pressure control valve (PCV)
4 Mechanical seal